[Automation] Which category after Cat0?Hi all,
Is it Cat3 that needs to be run on OOo320m4 once Cat0 is done ? Kind regards Sophie --------------------------------------------------------------------- To unsubscribe, e-mail: dev-unsubscribe@... For additional commands, e-mail: dev-help@... |
|
|
Re: [Automation] Which category after Cat0?Hi Sophie,
following the 'Automation Release Matrix'[1] you can (optionally) run as many autotests as you like starting with cat1 followed by cat2 and cat3 after running cat0 autotests. Hope that helps. Best Regards Helge [1]http://wiki.services.openoffice.org/wiki/OOoAutomationReleaseTestMatrix On 11/09/09 11:31, Sophie wrote: > Hi all, > > Is it Cat3 that needs to be run on OOo320m4 once Cat0 is done ? > > Kind regards > Sophie > > --------------------------------------------------------------------- > To unsubscribe, e-mail: dev-unsubscribe@... > For additional commands, e-mail: dev-help@... > -- =============================================================== Sun Microsystems GmbH Helge Delfs Nagelsweg 55 Quality Assurance Engineer 20097 Hamburg OOo Team Lead Automation http://qa.openoffice.org mailto:hde@... http://wiki.services.openoffice.org/wiki/User:Hde PGP Key-ID: 0x395940C4 --------------------------------------------------------------------- To unsubscribe, e-mail: dev-unsubscribe@... For additional commands, e-mail: dev-help@... |
|
|
Re: [Automation] Which category after Cat0?Hi Helge,
Helge Delfs wrote: > Hi Sophie, > > following the 'Automation Release Matrix'[1] you can (optionally) run as > many autotests as you like starting with cat1 followed by cat2 and cat3 > after running cat0 autotests. Thanks for your answer. There is still something unclear for me. If I go on this page [1], it is said that Cat1 is run on the first build, Cat2 on the second, and so on. Does it mean that for example for OOo320m1, I should have run Cat0 + Cat1 and for OOo320m2, Cat0 + Cat2, etc...? Kind regards Sophie [1]http://wiki.services.openoffice.org/wiki/QUASTe#Category_model > > Hope that helps. > > > Best Regards > Helge > > [1]http://wiki.services.openoffice.org/wiki/OOoAutomationReleaseTestMatrix > > > > > > On 11/09/09 11:31, Sophie wrote: >> Hi all, >> >> Is it Cat3 that needs to be run on OOo320m4 once Cat0 is done ? >> >> Kind regards >> Sophie >> >> --------------------------------------------------------------------- >> To unsubscribe, e-mail: dev-unsubscribe@... >> For additional commands, e-mail: dev-help@... >> > > --------------------------------------------------------------------- To unsubscribe, e-mail: dev-unsubscribe@... For additional commands, e-mail: dev-help@... |
|
|
Re: [Automation] Which category after Cat0?Hi Sophie,
On 11/09/09 16:24, Sophie wrote: > Thanks for your answer. There is still something unclear for me. If I go > on this page [1], it is said that Cat1 is run on the first build, Cat2 > on the second, and so on. Does it mean that for example for OOo320m1, I > should have run Cat0 + Cat1 and for OOo320m2, Cat0 + Cat2, etc...? The category model is not valid for 'release' workspaces (in this case OOO320) only for dev-workspaces (currently DEV300) We once decided that Cat0-Tests must be run error-free for releases, all other tests are optional. Regards Helge > Kind regards > Sophie > > [1]http://wiki.services.openoffice.org/wiki/QUASTe#Category_model >> >> Hope that helps. >> >> >> Best Regards >> Helge >> >> [1]http://wiki.services.openoffice.org/wiki/OOoAutomationReleaseTestMatrix >> >> >> >> >> >> >> On 11/09/09 11:31, Sophie wrote: >>> Hi all, >>> >>> Is it Cat3 that needs to be run on OOo320m4 once Cat0 is done ? >>> >>> Kind regards >>> Sophie >>> >>> --------------------------------------------------------------------- >>> To unsubscribe, e-mail: dev-unsubscribe@... >>> For additional commands, e-mail: dev-help@... >>> >> >> > > > --------------------------------------------------------------------- > To unsubscribe, e-mail: dev-unsubscribe@... > For additional commands, e-mail: dev-help@... > -- =============================================================== Sun Microsystems GmbH Helge Delfs Nagelsweg 55 Quality Assurance Engineer 20097 Hamburg OOo Team Lead Automation http://qa.openoffice.org mailto:hde@... http://wiki.services.openoffice.org/wiki/User:Hde PGP Key-ID: 0x395940C4 --------------------------------------------------------------------- To unsubscribe, e-mail: dev-unsubscribe@... For additional commands, e-mail: dev-help@... |
|
|
Re: [Automation] Which category after Cat0?Hi,
sorry, forgot to mention I've updated the wiki-page[1] :-) Regards Helge [1]http://wiki.services.openoffice.org/wiki/QUASTe#Category_model On 11/10/09 09:02, Helge Delfs wrote: > Hi Sophie, > > On 11/09/09 16:24, Sophie wrote: >> Thanks for your answer. There is still something unclear for me. If I go >> on this page [1], it is said that Cat1 is run on the first build, Cat2 >> on the second, and so on. Does it mean that for example for OOo320m1, I >> should have run Cat0 + Cat1 and for OOo320m2, Cat0 + Cat2, etc...? > > The category model is not valid for 'release' workspaces (in this case > OOO320) only for dev-workspaces (currently DEV300) > We once decided that Cat0-Tests must be run error-free for releases, all > other tests are optional. > > > Regards > Helge > > > >> Kind regards >> Sophie >> >> [1]http://wiki.services.openoffice.org/wiki/QUASTe#Category_model >>> Hope that helps. >>> >>> >>> Best Regards >>> Helge >>> >>> [1]http://wiki.services.openoffice.org/wiki/OOoAutomationReleaseTestMatrix >>> >>> >>> >>> >>> >>> >>> On 11/09/09 11:31, Sophie wrote: >>>> Hi all, >>>> >>>> Is it Cat3 that needs to be run on OOo320m4 once Cat0 is done ? >>>> >>>> Kind regards >>>> Sophie >>>> >>>> --------------------------------------------------------------------- >>>> To unsubscribe, e-mail: dev-unsubscribe@... >>>> For additional commands, e-mail: dev-help@... >>>> >>> >> >> --------------------------------------------------------------------- >> To unsubscribe, e-mail: dev-unsubscribe@... >> For additional commands, e-mail: dev-help@... >> > > -- =============================================================== Sun Microsystems GmbH Helge Delfs Nagelsweg 55 Quality Assurance Engineer 20097 Hamburg OOo Team Lead Automation http://qa.openoffice.org mailto:hde@... http://wiki.services.openoffice.org/wiki/User:Hde PGP Key-ID: 0x395940C4 --------------------------------------------------------------------- To unsubscribe, e-mail: dev-unsubscribe@... For additional commands, e-mail: dev-help@... |
|
|
Re: [Automation] Which category after Cat0?Hi Helge,
Helge Delfs wrote: > Hi Sophie, > > On 11/09/09 16:24, Sophie wrote: >> Thanks for your answer. There is still something unclear for me. If I go >> on this page [1], it is said that Cat1 is run on the first build, Cat2 >> on the second, and so on. Does it mean that for example for OOo320m1, I >> should have run Cat0 + Cat1 and for OOo320m2, Cat0 + Cat2, etc...? > > The category model is not valid for 'release' workspaces (in this case > OOO320) only for dev-workspaces (currently DEV300) > We once decided that Cat0-Tests must be run error-free for releases, all > other tests are optional. Ok, thanks for your answers. Kind regards Sophie --------------------------------------------------------------------- To unsubscribe, e-mail: dev-unsubscribe@... For additional commands, e-mail: dev-help@... |