Planner-list % completWas wondering why planner does not total the % complete of the parent task as it does for the days? Example:
Sergio _______________________________________________ Planner-list mailing list Planner-list@... http://mail.gnome.org/mailman/listinfo/planner-list |
||||||||||||||||||||||||||||||||||||||||
|
|
Re: Planner-list % completOn Sat, Oct 3, 2009 at 4:06 PM, sergio pereira
<sergioflorespereira@...> wrote: > Hi, Hi, > Was wondering why planner does not total the % complete of the parent task as it does for the days? Are you refering to https://bugzilla.gnome.org/show_bug.cgi?id=561000 ? -- Alexandre Franke _______________________________________________ Planner-list mailing list Planner-list@... http://mail.gnome.org/mailman/listinfo/planner-list |
||||||||||||||||||||||||||||||||||||||||
|
|
Re: Planner-list % completHi, The parent is the average of all child tasks, 580 / 7. _______________________________________________ Planner-list mailing list Planner-list@... http://mail.gnome.org/mailman/listinfo/planner-list |