|
View:
New views
7 Messages
—
Rating Filter:
Alert me
|
|
|
Planner-list predecessors for fixed date tasksHi all
Apologies for what's probably a newbie question. I'm trying to use Planner to manage academic grant applications. As such, there's a number of key tasks whose dates are externally set and non-negotiable (such as the date the grant must be submitted to the funding agency, or the date a letter of intent is due to the funding agency). I've been 'locking' these dates by creating a milestone task (eg "Submit grant") with a schedule of 'on fixed date' on the required date. The problem I'm having is when I try and link these milestone tasks to the rest of the tasks in the project by setting a predecessor. This produces the error "You cannot add a relationship to a task with a Must Start On constraint." I've also tried using a one-day task instead of a milestone task, but get the same error. Is there another approach to dealing with externally set fixed dates that I'm missing, or a way to set milestone tasks which allows linking to other tasks? Any suggestions would be most welcome. Regards Pete _______________________________________________ Planner-list mailing list Planner-list@... http://mail.gnome.org/mailman/listinfo/planner-list |
|
|
Re: Planner-list predecessors for fixed date tasksOn Sun, Oct 25, 2009 at 5:42 AM, pete davidson <caitifty@...> wrote:
> Hi all Hi, > I'm trying to use Planner to manage academic grant applications. As such, > there's a number of key tasks whose dates are externally set and > non-negotiable (such as the date the grant must be submitted to the funding > agency, or the date a letter of intent is due to the funding agency). I've > been 'locking' these dates by creating a milestone task (eg "Submit grant") > with a schedule of 'on fixed date' on the required date. > > The problem I'm having is when I try and link these milestone tasks to the > rest of the tasks in the project by setting a predecessor. This produces > the error "You cannot add a relationship to a task with a Must Start On > constraint." I've also tried using a one-day task instead of a milestone > task, but get the same error. The problem here is with the meaning of the predecessor relationship. If you set A as a predecessor of B, it means that you cannot start working on B until A is done. So what would happen if you start A on oct 26th, need 4 days to finish it and set B on oct 28th (fixed date)? That wouldn't make any sense because you'd need to work on B but you couldn't since A isn't done yet. This has nothing to do with the fact that it's a milestone. > Is there another approach to dealing with externally set fixed dates that > I'm missing, or a way to set milestone tasks which allows linking to other > tasks? You can do it without the predecessor relationship, I think it's the way that would make the most sense. -- Alexandre Franke _______________________________________________ Planner-list mailing list Planner-list@... http://mail.gnome.org/mailman/listinfo/planner-list |
|
|
Re: Planner-list predecessors for fixed date tasksI'm not sure to understand, but my comment could help. if you have a "Deadline" task for a part of your project (including, for exemple, task A) - you can set "Deadline" task as a fixed date milestone - of course you can't set any predecessor for this fixed date task - so you can't set A as predecessor (for example "end to start" link) for "Deadline" task, but... - you can set "Deadline" task as predecessor (same example ; "start to end" link) of A limits for this example : - even if A is an "as soon as possible" task, it will be scheduled to "the last moment" before "Deadline". why ? we just wan't it to become a "not after" task. - you can't anticipate A setting it to fixed date (today for example). why ? - you can't set any other predecessor to A (a current task ending tomorrow, linked "end to start", for example), even if A has been scheduled on next year. why ? I agree that external constraints are decisive in project scheduling and that Planner constraints rules are too much restrictive. but it's not an easy problem, and coding realy accurate rules could be an infinite task. so just try to use such links with parsimony Regards, Ricardo FERNANDEZ De : Alexandre Franke alexandre.franke@...
Envoyé : 25/10/2009 13:14:00 +0100
À : planner planner-list@...
Objet : Planner-list predecessors for fixed date tasks
On Sun, Oct 25, 2009 at 5:42 AM, pete davidson caitifty@... wrote: _______________________________________________ Planner-list mailing list Planner-list@... http://mail.gnome.org/mailman/listinfo/planner-list |
|
|
Re: Planner-list predecessors for fixed date tasksOn Wed, 2009-10-28 at 23:08 +0100, Ricardo Fernandez wrote:
> Hello Pete, > > I'm not sure to understand, but my comment could help. > > if you have a "Deadline" task for a part of your project (including, > for exemple, task A) > - you can set "Deadline" task as a fixed date milestone > - of course you can't set any predecessor for this fixed date task > - so you can't set A as predecessor (for example "end to start" link) > for "Deadline" task, but... > - you can set "Deadline" task as predecessor (same example ; "start > to end" link) of A > set up the deadline as a predecessor with a 'SF' relationship. Task A will then be scheduled so that it ends just prior to the deadline task. > limits for this example : > - even if A is an "as soon as possible" task, it will be scheduled to > "the last moment" before "Deadline". why ? we just wan't it to become > a "not after" task. ASAP just means that the task start date will float based on predecessor relationships. Planner schedules all tasks (without assigned resources) assuming that a single resource will work at 100% capacity for the duration, and sets the start and end dates accordingly. If you want to change the start date on a task with a 'SF' relationship, you should assign a resource and adjust the resource units to something less than 100%. > - you can't anticipate A setting it to fixed date (today for > example). why ? see above > - you can't set any other predecessor to A (a current task ending > tomorrow, linked "end to start", for example), even if A has been > scheduled on next year. why ? > Well, if you've set the finish date for task A with a SF or FF relationship, then we need to let the start date float in order for the scheduling algorithm to work. If you created a task B, you could set task A as a predecessor with a SF or FF relationship. In this way, you're essentially scheduling from the deadline back to the present day. > I agree that external constraints are decisive in project scheduling > and that Planner constraints rules are too much restrictive. > but it's not an easy problem, and coding realy accurate rules could be > an infinite task. > > so just try to use such links with parsimony > > Regards, > Ricardo FERNANDEZ > > > > ______________________________________________________________________ > De : Alexandre Franke <alexandre.franke@...> > Envoyé : 25/10/2009 13:14:00 +0100 > À : planner <planner-list@...> > Objet : Planner-list predecessors for fixed date tasks > > > On Sun, Oct 25, 2009 at 5:42 AM, pete davidson <caitifty@...> wrote: > > > > > Hi all > > > > > > > Hi, > > > > > > > I'm trying to use Planner to manage academic grant applications. As such, > > > there's a number of key tasks whose dates are externally set and > > > non-negotiable (such as the date the grant must be submitted to the funding > > > agency, or the date a letter of intent is due to the funding agency). I've > > > been 'locking' these dates by creating a milestone task (eg "Submit grant") > > > with a schedule of 'on fixed date' on the required date. > > > > > > The problem I'm having is when I try and link these milestone tasks to the > > > rest of the tasks in the project by setting a predecessor. This produces > > > the error "You cannot add a relationship to a task with a Must Start On > > > constraint." I've also tried using a one-day task instead of a milestone > > > task, but get the same error. > > > > > > > The problem here is with the meaning of the predecessor relationship. > > If you set A as a predecessor of B, it means that you cannot start > > working on B until A is done. So what would happen if you start A on > > oct 26th, need 4 days to finish it and set B on oct 28th (fixed date)? > > That wouldn't make any sense because you'd need to work on B but you > > couldn't since A isn't done yet. > > > > This has nothing to do with the fact that it's a milestone. > > > > > > > Is there another approach to dealing with externally set fixed dates that > > > I'm missing, or a way to set milestone tasks which allows linking to other > > > tasks? > > > > > > > You can do it without the predecessor relationship, I think it's the > > way that would make the most sense. > > > > > _______________________________________________ > Planner-list mailing list > Planner-list@... > http://mail.gnome.org/mailman/listinfo/planner-list _______________________________________________ Planner-list mailing list Planner-list@... http://mail.gnome.org/mailman/listinfo/planner-list |
|
|
Re: Planner-list predecessors for fixed date tasksIf you want to change the start date on a task with a 'SF' relationship, you should assign a resource and adjust the resource units to something less than 100%.problem : using resources this way turns it to nothing more than an abstract parameter. Well, if you've set the finish date for task A with a SF or FF relationship, then we need to let the start date floatThat's precisely the question : the finish date for task A is then set and fixed. both start date and finish date for task A sould be floating two rules can be imagined to define SF links : - end(A) < start(Deadline) ; that's the minimal constraint and so the more usefull (and generally the actual logical link). - end(A) = start(Deadline) ; that's the maximal constraint for an SF link, and the Planner's one. generally too restrictive. the less restrictive is a tool, the more useful it is... and the more complex is the algorithm. is there any way to centralize a collective analyze and specification for algorithm evolution ? is there any conceptual documentation (exept code and its comments) for link rules and sheduling algorithm ? I have no time (like everyone) but should be interessed (probably like some others) to contribute to a conceptual specification Planner is no far away from being an excelent simple and intuitive tool but, to be honest, I'm not acheaving to use it efficiently at this time Regards, Ricardo FERNANDEZ De : Kurt Maute kurt@...
Envoyé : 29/10/2009 14:35:30 +0100
À : Ricardo Fernandez
ricardo.fernandez@...
Copie : pete davidson caitifty@..., planner
planner-list@...
Objet : Planner-list predecessors for fixed date tasks
On Wed, 2009-10-28 at 23:08 +0100, Ricardo Fernandez wrote: _______________________________________________ Planner-list mailing list Planner-list@... http://mail.gnome.org/mailman/listinfo/planner-list |
|
|
Re: Planner-list predecessors for fixed date tasksOn Fri, Oct 30, 2009 at 01:14:35AM +0100, Ricardo Fernandez wrote:
> is there any way to centralize a collective analyze and specification > for algorithm evolution ? > is there any conceptual documentation (exept code and its comments) for > link rules and sheduling algorithm ? > I have no time (like everyone) but should be interessed (probably like > some others) to contribute to a conceptual specification The problem is not in coming up with an idea for scheduling, it is in finding someone who is willing to work on it and stick with it. When thinking about how scheduling should work it quickly pulls in many many other things that ideal scheduling functionality requires, such as split tasks. The bigger the ideas and requirements get, the more motivation you need to actually take on the problem of implementation. Additionally it is harder to motivate someone to implement other people's requirements than it is to get them to implement their own. In my opinion discussing requirements like this will go nowhere unless the one starting the discussion is the one who plans to implement it. Look through bugzilla for this feature, you'll see what I mean. Regards, Maurice. -- Maurice van der Pot Gentoo Linux Developer griffon26@... http://www.gentoo.org Gnome Planner Developer griffon26@... http://live.gnome.org/Planner _______________________________________________ Planner-list mailing list Planner-list@... http://mail.gnome.org/mailman/listinfo/planner-list |
|
|
Re: Planner-list predecessors for fixed date tasksDe : Maurice van der Pot griffon26@...
Envoyé : 30/10/2009 18:11:50 +0100
À : planner-list@...
Objet : Planner-list predecessors for fixed date tasks
I totally agree ; remember my sentense just before your extract :On Fri, Oct 30, 2009 at 01:14:35AM +0100, Ricardo Fernandez wrote: " the less restrictive is a tool, the more useful it is... and the more complex is the algorithm." and spliting tasks (for example) was to my mind an absolute necessity for schedulling taking ressources in account. ok for 'big ideas'.The bigger the ideas and requirements get, the more motivation you need to actually take on the problem of implementation. concerning requirements and precise specifications, instead, I thought it could help implementation as well as motivation. that's done !Additionally it is harder to motivate someone to implement other people's requirements than it is to get them to implement their own. In my opinion discussing requirements like this will go nowhere unless the one starting the discussion is the one who plans to implement it. Look through bugzilla for this feature, you'll see what I mean. and that's precisely why I suggested another way of work. in conclusion, I fear that those who hope Planner can become the accurate tool they need, there are two options : - discussion list ; a waste of time - waiting for developpers to find time and motivation... Regards Ricardo FERNANDEZ Regards, Maurice. _______________________________________________ Planner-list mailing list Planner-list@... http://mail.gnome.org/mailman/listinfo/planner-list |
| Free embeddable forum powered by Nabble | Forum Help |