Maurice,
Yes, some of the tasks were marked 100% before this issue appeared. I
have not been successful with incrementing any task. Try task #25
Vacation August.
I could not get beyond 75% when using the "Edit task properties" dialog.
I was unaware that the completion could be dragged. Dragging the
completion to 100% seems to work, but the "Edit task properties" dialog
still shows 75% complete.
I have not figured out how to enable the task complete column.
This may be related to the Fedora 9 upgrade from 7. I have had some
other problems. I am going to do a fresh install of Fedora 9 on another
disk and see if the issue still exists.
Regards,
Peter F
-----Original Message-----
From:
planner-list-bounces@...
[mailto:
planner-list-bounces@...] On Behalf Of Maurice van der Pot
Sent: Wednesday, August 20, 2008 2:05 PM
To:
planner-list@...
Subject: Re: Planner-list Task Complete goes to 75% max
I've looked at the planner file you sent me, but I've been unable to
reproduce the problem.
A few more questions:
- Does the problem occur with all tasks?
I see some of the tasks in the file already have a completion > 75%
- Does the problem occur with newly created files?
- Do none of the ways of changing completion work:
* dragging completion in the gantt chart?
* using the "Edit task properties" dialog?
* enabling the "% Complete" column next to the gantt chart and editing
there?
Regards,
Maurice.
--
Maurice van der Pot
Gentoo Linux Developer
griffon26@... http://www.gentoo.orgGnome Planner Developer
griffon26@...
http://live.gnome.org/Planner_______________________________________________
Planner-list mailing list
Planner-list@...
http://mail.gnome.org/mailman/listinfo/planner-list