Hi
Sorry, but there must be something fundamental in kplato I have missed. I hope
someone might be able to help.
I have made one resource(person), one calendar and a few tasks which are all
assigned to the one resource.
I then expect that when I hit the "Calculate" button that kplato would
schedule the tasks so that they don't overlap (the one resource I have should
only work 8 hours a day...). However this doesn't work.
When I hit the "Calculate" button I instead get cryptic messages in the log
like:
"Could not match effort. Want 16h0m got 0h0m"
"Resource vl available from 05/18/09 12:00am to 05/18/11 04:00pm"
"Resource vl not available in interval: 05/18/09 12:00am to 05/18/09 04:00pm"
All tasks is defined "As soon as possible", no fixed dates.
Clicking on view->Resource assignments shows 0.0 in total for my resource so
there might some mapping between resource and tasks I have missed ?
I have attached my test project in the email( not sure it will get through to
the mailing list though)
I am using KOffice 2.0RC-1 from Kubuntu/Jaunty
(KPlato v.0.6.99)
Best regards,
Vidar
--